Nottawasaga Valley Conservation Authority (NVCA) is requesting proposals from qualified professional engineers for the update of the Dyke Safety Review for Pretty River Dyke.
Sealed proposals will be received by the undersigned on behalf of the NVCA as follows:
Bidders are encouraged to use electronic means for delivering proposals. Electronic proposals will be delivered in a PDF format with “Confidential – RFP #01/2023 Nottawasaga Valley Conservation Authority Pretty River Dyke Safety Review Update” in the subject line. For hard copy delivery, one (1) hard copy is to be submitted, in a sealed envelope clearly marked “Confidential – RFP #01/2023 Nottawasaga Valley Conservation Authority Pretty River Dyke Safety Review Update”.
The completed quotations will be received until 4:00 p.m. local eastern standard time on October 6, 2023, by:
Chris Hibberd
Director, Watershed Management Services
Nottawasaga Valley Conservation Authority
John Hix Conservation Administration Centre 8195 8th Line, Utopia, Ontario
L0M 1T0
Proposals via fax cannot be accepted.
This time and date will be deemed to be the closing of the proposal. Late proposals will not be considered.
Please note that the lowest proposal will not necessarily be successful or accepted. The NVCA reserves the right to accept any proposal or to reject any or all proposals. NVCA reserves the right to accept more than one contract.
The selection is anticipated to take place by the second week of October with the successful bidder being notified after this time. Only the successful candidate will be notified.
For more information or for a copy of this document in an alternative format, please contact NVCA at 705-424-1479 or c.hibberd@nvca.on.ca
Addendum #1
Pretty River Flood Control Study – Oct 21 1987
Pretty River Flood Control Study Stage 3 (Image 1)
Pretty River Flood Control Study Stage 3 (Image 2)
Pretty River Flood Control Study Stage 3 (Image 3)
Pretty River Flood Control Study Stage 3 (Image 4)
Pretty River Flood Control Study Stage 3 (Image 5)
Pretty River Flood Control Study Stage 3 (Image 6)
Pretty River Flood Control Study Stage 3 (Image 7)
Pretty River Flood Control Study Stage 3 (Image 8)
Pretty River Flood Control Study Stage 3 (Image 9)
Addendum #2
Pretty River Dike Inspection Notes – October 26, 2020